Who must be notified of the date of completion of a building?

Prepare for the BCIN Designer Legal/Process Exam. Utilize flashcards and multiple choice questions, each with hints and detailed explanations. Be confident and ready for your test!

The correct answer is that the chief building official or a registered code agency must be notified of the date of completion of a building. This notification is crucial because it allows the building authority to carry out necessary inspections, review compliance with building codes, and ensure that all aspects of the construction meet safety and regulatory requirements.

The role of the chief building official or a registered code agency is to oversee public safety and the enforcement of building laws. Notifying them helps maintain proper records and ensures that the project adheres to the applicable regulations throughout its lifecycle. This notification is part of due diligence in the construction process, reinforcing the importance of accountability and communication with the governing authorities.

Other stakeholders, like the local municipality, project architect, and construction crew, play important roles in the construction process, but they are not specifically mandated to receive notification regarding the completion of the building. Instead, the focus is on regulatory compliance and the monitoring of safety standards, which places the responsibility clearly on the chief building official or the designated code agency.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy